Eversource work on Sundays approved for Stepstone to Green Hill Substation Upgrade Project

The Connecticut Siting Council approved Sunday work hours for the Eversource Stepstone to Green Hill Substation Upgrade
Project on May 20, June 10, 17, 24 and July 15, 2018.  All Sunday work would be performed from 8 a.m. to 5 p.m. and would include structure installation, transferring the conductor, removing existing structures and pulling optical ground wire in Guilford and Madison during scheduled outages.  The change in work hours is necessary due to changes in the outage schedule.  This approval applies only to the request for changes to work hours dated May 10, 2018.  Any significant changes to the project require advance Council notification and approval.

Posted in Alerts