Connecticut Water Projects Continue in Town

Connecticut Water Projects are continuing through the remainder of the 2020 construction season. Main installation on Boston Street will end just prior to Park Street. Once that is complete, the main will be tested and cleared and services will be changed over to the newly installed section.

Final road restoration (milling and paving) will take place from South Union to Park Street. If time remains prior to winter weather, work will begin on the main installation from Jacobs Lane toward the East River Bridge.

Update Project Map